Serica Energy has provided an operational update for the Rhum R3 well, confirming that new completion equipment has been successfully installed and a flow test has now been performed.
A stabilised flow rate of 58.4mmscf per day of gas and 135 barrels per day of condensate was achieved, though the rate was constrained by the surface well test equipment on board the WilPhoenix semi-submersible drilling rig and it is expected that the well will be able to produce at higher rates when in production.
A diving support vessel has been contracted to install the subsea control equipment required so the well can start producing in Q3 2021. Read more…