Summary tables

Concise overviews of environmental requirements for Oil & Gas activities

Offshore Activities

Geological and Seismic SurveyDrilling a WellWell TestWorkoverNew Offshore PipelineNew Project or ModificationProductionChemical PermitsOffshore Waste Storage and TransferOil and Chemical SpillsDecommissioningDecommissioning

TimelineRequirement / Action
What Consents Required for Geological and Seismic Surveys
Consent to Survey required for: Seismic survey; high resolution seismic site survey; borehole seismic; shallow drilling; and gravity/magnetic survey.
Notification of Survey required for: new pipeline or cable route survey; seabed survey not around existing installation or pipeline; all surveys near or in a "relevant site" under the Regulations.
No Action required for: inspection, repair and maintenance survey; surveys of existing pipelines or installations; pre/post lay environmental survey.
Survey Planning & Consents Timeline
6+ monthsIdentify if any conditions on seismic survey are detailed in licence conditions.
6+ monthsIdentify if survey is in an area sensitive to cetaceans and/or near a site designated under the Habitats Directive. Early discussions with JNCC/DESNZ suggested. An EIA and Habitats Regulatory Assessment may be needed.
6+ monthsIdentify if any important fishing grounds are in the survey area.
6+ monthsIf necessary, undertake EIA and prepare Environmental Statement (ES).
6+ monthsIdentify survey window to minimise environmental impacts.
2 monthsIf applicable, prepare standalone permit submission.
3 monthsIf applicable, submit Standalone Survey Consent to DESNZ.
1 monthIf applicable, submit Notification of Survey.
Survey(Survey work takes place)
Key Compliance During Seismic Survey
At least 30 minutes before operations, check visually for marine mammals within 500 m of vessel. Hydrophones may also be used in poor visibility.
If marine mammals are present, delay start until they have moved away. Allow at least 20 minutes after last sighting before starting operations.
Where equipment allows, build power up slowly from a low energy start, allowing 20 minutes for mammals to move out of range. Start at least 500 m away from seals around platforms.
Use the lowest practicable power levels throughout the survey.


TimelineRequirement / Action
Drilling a Well – Consent Requirements
An Environmental Statement is required for any drilling in near shore or sensitive areas. Drilling associated with a new development is also likely to require an ES. If unsure, discussions should be held with DESNZ or a Drilling Operations Application (DRA) can be used to seek a dispensation.
12+ monthsIf required, submit DRA to determine requirement for an Environmental Statement. This step can be skipped if it is clear that an ES is or is not required.
12+ monthsUndertake Environmental Impact Assessment (EIA) and prepare ES.
12+ monthsIdentify if proposed drilling occurs near habitats or protected species under EU Habitats Directive. Additional measures and Habitats Regulatory Assessment may be required.
12+ monthsIf no asset-wide Oil Pollution Emergency Plan is in place, prepare OPEP.
4 monthsIf no asset-wide Oil Pollution Emergency Plan is in place, prepare OPEP.
3 monthsPrepare Chemical Permit SAT (DRA) and environmental information sections, including any chemical use/discharge associated with well cleanup if applicable.
SubmissionSubmit ES along with Application for Consent (PON16).
2 monthsSubmit OPEP to DESNZ for approval.
3–5 weeksIf reinjection of cuttings planned offsite, submit application for reinjection under FEPA.
28 daysSubmit Chemical Permit SAT (DRA). Ensure chemicals are registered with CEFAS and replace high-risk chemicals where possible.
28 daysSubmit PON4 (Consent to Drill Well).
28 daysMake application to DTLR for Consent to Locate for rig (as part of DRA application).
28 daysIf Deposit of Stabilisation and Protection Materials required, submit application under EIA Regulations to deposit material on the seabed (as part of DRA application).
28 daysIf drilling through pay-zone and reservoir hydrocarbon contamination of drill cuttings for overboard discharge expected, apply for Oil Discharge Permit. Permit may also be required if OBM well cleanup is expected or any oil contamination of WBM/SBM cleanup.
1 weekAny radioactive sources will need a Certificate of Registration.
Spud Date
Key Compliance During Drilling
Ensure compliance with any licence, exemption or consent permit conditions, including commitments made in ES.
Ensure spill prevention and oil spill response procedures are introduced to rig personnel and appropriate equipment is in place.
Use only the permitted chemicals and mud system.
If reinjecting cuttings, ensure alternative legal disposal methods are in place as backup if CRI fails.
Routinely monitor base fluid use and discharge and sample and analyse cuttings for oil content. Report findings to DESNZ.
Use technology and other techniques to prevent or reduce discharges of all chemicals. Monitor and report all chemical use via EEMS.
Ensure compliance with Oil Discharge Permit. Minimise possibility of contaminated fluid discharge. If discharging cuttings overboard, ensure no contamination with oil unless a permit is in place.
Undertake seabed environmental surveys as required by DESNZ.
Report any accidental discharge of oil, including OBM or SBM, to DESNZ.
Report any accidental discharge of chemicals, including drilling muds, to DESNZ.
Undertake all statutory reporting and EEMS reporting for each activity.
Ensure renewed permit is in place if the planned well continues beyond expiry date of the initial permit.
Rig Compliance (Non-Drilling)
Undertake a pre-mobilisation audit of the drilling rig to ensure environmental compliance for drilling and non-drilling operations.
Machinery space drainage: ensure oil content of discharge meets the 15 ppm standard. Maintain Oil Record Book.
Diesel engines and generators: maintain record of fuel use.
No limits on sewage and cooling water discharges.
No garbage (including plastic) to be disposed of overboard. Only comminuted food waste can be discharged.
Ensure compliance with waste disposal licences, garbage management plan, and documentation requirements. Reuse or recycling is preferred.
Ensure compliance with legislation for disposal of drill cuttings, including reinjection, overboard disposal (WBM only), or transfer to shore.


TimelineRequirement / Action
Well Test – Consent Requirements
n/a (Well Test)Determine requirement for an Environmental Statement (ES) by submission of environmental information sections of Master Application Template (MAT).*
n/a (Well Test)If ES is required, undertake Environmental Impact Assessment (EIA) and prepare ES.
9 months (Extended Well Test)Determine requirement for an Environmental Statement (ES) by submission of environmental information sections of Master Application Template (MAT).*
9 months (Extended Well Test)If ES is required, undertake Environmental Impact Assessment (EIA) and prepare ES.
4 monthsIf no asset-wide Oil Pollution Emergency Plan (OPEP) is in place, prepare OPEP.
3 months (Extended Well Test)Submit ES along with Application for Consent for Test Production (PON16).
2 monthsSubmit OPEP (if needed) to DESNZ for approval.
Well Test* Drilling Operations Application (DRA) for well test from MODU and Production Operations Application (PRA) for platform or within 500 m of platform.
Key Compliance During Well Test
Use efficient burners and consider the need for the well test.
If undertaking extended well test, ensure that the rate of oil production complies with the requirements of the Consent for Test Production.
If undertaking extended well test, make monthly reports to the regulatory authority detailing the previous month’s test results. Notify the authority on completion and inform them of the production status of the well.
If flare drop-out occurs during well test operation, cease operations and report oil spill via PON1 to DESNZ. Note: a permit/exemption is no longer required for flare drop-out.


TimelineRequirement / Action
Workover – Consent Requirements
4–5 monthsApply for a Certificate of Registration if any radioactive sources are to be used.
28 daysApply for an Oil Discharge Permit for oily discharges.
28 daysSubmit a Well Intervention Operations Application (WIA) for any chemicals to be used or discharged, including any consideration of OBM well clean up if applicable.
WorkoverNote: WIA can also now be an annual permit for ongoing platform well interventions and workovers.
Key Compliance During Workover
Ensure monitoring of oil in water content of any discharge takes place.
If oil is detected in discharge, report total quantity of oil and water discharged during operation to DESNZ.
Cease operation if free oil is seen on the sea surface and report as an oil spill via PON1.
Ensure a renewed permit is in place if the planned workover operation continues beyond expiry of the initial permit.


TimelineRequirement / Action
Approval for New Pipeline – Consent Requirements
> 12 months (depends on size of development)Determine requirement for an Environmental Statement (ES). ES is mandatory for pipelines >40 km length and 800 mm diameter. Smaller pipelines may still require ES if part of a wider development.
> 12 monthsUndertake Environmental Impact Assessment (EIA) and prepare ES.
> 12 monthsUndertake informal consultation with statutory consultees, DESNZ, JNCC, and MS/CEFAS.
> 12 monthsUndertake early consultation with fishing interests.
> 12 monthsIdentify if development is near habitats or protected species under the EU Habitats Directive. Additional measures and a Habitats Regulatory Assessment may be required.
> 12 monthsPrepare environmental information (and possibly chemical permit application) section of PLA.
n/a / 4–5 monthsPrepare environmental information (and possibly chemical permit application) section of PLA.
4 monthsSubmit Pipeline Works Authorisation, which includes application for Consent to Locate and Consent to Deposit Materials for pipeline stabilisation.
4 monthsSubmit ES along with Pipeline Works Authorisation.
28 daysPrepare and submit application for PLA for any chemicals to be used and discharged during pipeline commissioning.
Pipeline Construction(Construction and commissioning phase begins.)
Key Compliance During Pipelay
Ensure all commitments made in ES submitted to DESNZ are met in detailed design and implementation of pipeline installation and operation.
Ensure pipelay and other vessels have UK Oil Pollution Prevention Certificate (UKOPP) or IOPP. Ensure appropriate Garbage Management Plans are in place.
Remove any deposited stabilisation material if required by the regulator due to obstruction or hazard to other sea users.
Monitor and record use and discharge of all chemicals. Report quantities via EEMS.
Monitor and record all waste generated. Maintain records and meet disposal requirements for non-hazardous and hazardous waste.


TimelineRequirement / Action
Approval for New Project or Major Modification – Consent Requirements
> 12 monthsDetermine requirement for an Environmental Statement (ES) by submission of Production Operations Application (PRA). An ES is mandatory for all new fields and for new or increased production of over 500 tonnes of oil or 500,000 m³ gas per day.
> 12 monthsUndertake informal consultation with statutory consultees, DESNZ, JNCC, and MS/CEFAS.
> 12 monthsIdentify if development occurs near habitats or protected species under EU Habitats Directive. Additional measures and a Habitats Regulatory Assessment may be required.
n/aUndertake Environmental Impact Assessment (EIA) and prepare ES.
6 monthsApply in writing to DESNZ for Consent to Locate for fixed installation.
n/aPrepare environmental information section of PRA.
n/a / 4 monthsSubmit Production Operations Application (PRA) along with Application for Consent (PON16).
3 monthsSubmit ES along with Application for Consent (PON16).
Project ApprovalAlso see summary tables for Production Consents and New Pipeline if appropriate.
Key Compliance
Ensure all commitments made within ES submitted to DESNZ are met in detailed design and implementation of the project or modification.
Ensure all production or other consents are met (see Production Consents).


TimelineRequirement / Action
Production – Consent Requirements
-Ensure approval in place for New Project or Major Modification.
-Ozone depleting substances and fluorinated GHGs. Ensure halon use meets strict controls, especially in firefighting systems and refrigerants.
6 monthsPrepare PPC Application for any new combustion plant exceeding 50 MW(th) or if substantial change to existing plant. Submit EU ETS registration and allocation application to DESNZ.
5 monthsUndertake risk assessments and prepare Production Operations Application (PRA). Ensure chemicals are CEFAS-registered and replace high-risk ones where possible.
4 monthsIf radioactive sources are to be used, submit application for Certificate of Registration to SEPA/EA.
4 monthsIf no asset-wide Oil Pollution Emergency Plan (OPEP) is in place, prepare one.
3 monthsSubmit PPC Application.
3 monthsSubmit Chemical Permit Application (PRA).
2 monthsSubmit application for Consent to Flare to DESNZ.
2 monthsSubmit application for Consent to Vent to DESNZ.
2 monthsSubmit OPEP to DESNZ for approval.
28 daysSubmit Application for Oil Discharge Permit for produced water discharge (and other oil to sea e.g. drainage). Application required even if PWRI planned.
28 daysInclude in Oil Discharge Permit any produced sand and LSA discharge if oil contamination expected.
28 daysEnsure installation has a valid Garbage Management Plan in place.
28 daysIf new production facility, ensure a valid UK Oil Pollution Prevention Certificate (UKOPP) is held for oily machinery space drainage.
First Oil(Operations commence.)
Key Compliance During Production
Ensure oil content and total volume of produced water discharge meets Oil Discharge Permit requirements.
Undertake routine sampling and analysis of produced water with monthly reporting.
Undertake routine sampling and analysis of produced sand with quarterly reporting.
Machinery space drainage: ensure oil content of discharge meets 15 ppm standard. Record and keep Oil Record Book entries for 3 years.
Combustion plant: monitor and report emissions as required by permit. Report via EEMS.
Record quantities of crude oil stored, loaded, and offloaded. Calculate VOC emissions and report annually. Follow guidance for VOC reduction.
Ensure flaring and venting volumes comply with consents. Report via EEMS and notify DESNZ of any compliance failures.
Ensure EU ETS reporting and annual verification of emissions and improvements.
Use technology to prevent/reduce chemical discharges. Monitor and report via EEMS.
Report any accidental oil discharge to sea to HM Coastguard and DESNZ using PON1.
Report any accidental chemical discharge to DESNZ using PON1.
Keep OPEP up to date and undertake routine response training and exercises.
No current limits on sewage and cooling water discharges.
No garbage (including plastics) to be disposed of overboard. Only comminuted food waste may be discharged.
Ensure Garbage Management Plan is in place.
Maintain records of waste types and quantities. Report as required. Ensure correct documentation for transfer of waste (including special and hazardous waste) to shore.


TimelineRequirement / Action
Use of Chemicals – Consent Requirements
-Under the Offshore Chemical Regulations 2002, all chemicals (including drilling muds) require a consent to discharge. Chemicals must be registered with CEFAS and selected through a risk-based approach. Different Master Application Templates (MATs) apply for drilling, pipelines, platforms, decommissioning, and workovers.
4 monthsIdentify chemical requirements and ensure all chemicals are registered with CEFAS (i.e. full HOCNF data set available).
4 monthsEnsure chemicals selected are registered with CEFAS and those of high environmental risk are replaced where possible.
4 monthsUndertake risk assessment and CHARM modelling for chemicals not on the OSPAR PLONOR list. Substitute any high-risk chemicals.
4 monthsPrepare the appropriate Master Application Template (MAT). Environmental information is required for all applications, even if an ES has not been submitted.
28 daysSubmit the appropriate MAT to DESNZ.
Chemical Use or Discharge(Covers the application and approval process for chemical use.)
Key Compliance
Use technology and other techniques to prevent or reduce chemical discharges.
Provide justification for all chemicals flagged for substitution. Encourage suppliers to identify alternatives.
Monitor and record use and discharge of all chemicals. Report quantities via EEMS.
Report any chemical spills to DESNZ using PON1.
Submit annual substitution spreadsheets identifying all priority action or candidate substitution chemicals used and/or discharged during the year.


TimelineRequirement / Action
Offshore Waste Storage and Transfer – Consent Requirements
Before Waste GenerationEnsure Garbage Management Plan and appropriate procedures are in place.
Before Waste GenerationEnsure any Certificate of Authorisation for Accumulation and Disposal of Radioactive Waste is in place (if required). A separate certificate may be required for overboard disposal of LSA liquid waste.
Before Waste GenerationIf necessary, ensure registration with SEPA/EA for recycling of packaging waste and that recovery obligations are met.
Before Waste GenerationIf installing a shipboard incinerator for garbage, ensure it complies with Regulation 16 Annex VI of MARPOL.
Before Waste TransferEnsure Transfer Notes for any Controlled Waste transfer to shore are completed.
Before Waste TransferEnsure Consignment Notes for Special/Hazardous Waste are completed. Waste must be correctly marked and labelled for onshore requirements and IMDG Code compliance.
Before Waste TransferEnsure correct Transportation Records are completed for any Radioactive Waste.
Key Compliance for Offshore Waste Storage
Ensure waste is correctly segregated to support recycling/reuse and transport to shore.
Ensure appropriate authorisations and placards are displayed.
No overboard disposal of garbage. Waste must be contained and secured to prevent loss overboard.
Encourage waste minimisation and recycling/reuse/recovery as far as possible.
Ensure all Transfer Notes and Consignment Notes are retained as required.


Event / TimelineRequirement / Action
Oil and Chemical Spills – Contingency Planning and Reporting
2 – 4 months before operationEnsure an Oil Pollution Emergency Plan (OPEP) is in place. Currently no statutory requirement for chemical spill planning, but this may be included in the OPEP.
2 – 4 months before operationEnsure any vessel has an appropriate Ship Oil Pollution Emergency Plan (SOPEP) in place.
In event of spillReport any oil spill or accidental chemical spill immediately to DESNZ and HM Coastguard using PON1. Additional external reporting is required for oil spills. All spills must also be reported internally.
In event of spillIf there is an excursion to a chemical permit, do not report on PON1. Instead, report to DESNZ within at least 2 days of the incident. Best practice is to submit a variation to the permit before an excursion occurs and ensure out-of-hours contacts are available.
In event of spillMobilise appropriate response measures as set out in the OPEP.
Key Ongoing Compliance
Ensure appropriate spill prevention and response measures are in place.
Undertake regular oil and chemical spill response exercises as detailed in the OPEP.
Ensure all personnel are trained in spill prevention, reporting, and response measures.


Timeline / EventRequirement / Action
Decommissioning – Consent Requirements
3–5 yearsHold preliminary meeting with BEIS regarding the Decommissioning Programme. Schedule events and review options for pipelines and installations.
3 yearsDescribe and quantify materials on the structure, including chemical inventory. Identify possible decommissioning options and disposal routes.
3 yearsUndertake comparative environmental assessment of decommissioning options.
3 yearsIdentify if the project is in a designated habitat area and assess potential impacts. Consult with JNCC.
3 yearsIf planning to leave pipeline in situ, undertake a study on exposure and environmental impacts.
3 yearsIf applying for derogation, prepare a Derogation Case.
3 yearsPrepare 1st draft of Decommissioning Programme.
24 monthsSubmit 1st draft of Decommissioning Programme. BEIS consults Government Departments including MS/CEFAS, DETR, SEPA/EA, JNCC, and HSE.
21 monthsReceive BEIS feedback on 1st draft. (If applying for derogation, process may take longer.)
18 monthsSubmit 2nd draft of Decommissioning Programme. BEIS re-consults with relevant Government Departments.
18 monthsOperator circulates proposals to statutory consultees and publishes in press/online. Statutory consultees have 30 days to comment.
18 monthsConsider need for baseline environmental survey if no prior data exists.
16 monthsReceive BEIS feedback on 2nd draft of Decommissioning Programme.
12 monthsSubmit final draft of Decommissioning Programme, including consultation outcomes.
12 monthsSubmit application for an Oil Discharge Permit (if oily discharges expected).
12 monthsSubmit application for Disposal of Material under FEPA (if seabed deposits anticipated).
12 monthsConsult SEPA/EA for waste disposal licences.
4–6 monthsReceive written approval of the Decommissioning Programme from BEIS.
4 monthsSubmit Decommissioning Operations Application (DCA) for chemicals to be used or discharged.
6 weeksProvide Notice of Change of Status of pipeline/installation to the UK Hydrographic Office.
DecommissioningAlso see Well Abandonment requirements if applicable.
Key Compliance Post Decommissioning
Where pipelines or installations are left in place, submit locational data and surveyed depths to the Hydrographic Office. Install and maintain navigational aids for any remains above sea surface.
Segregate hazardous (e.g. oily waste, asbestos, chemicals) and non-hazardous wastes. Keep records of hazardous waste and consignment notes.
Comply with all waste disposal licences and transfer documentation. Reuse or recycling is preferred.
Undertake an independent debris clearance verification survey.
Conduct post-decommissioning seabed sampling survey for hydrocarbons, heavy metals, and contaminants. Survey strategy agreed with BEIS.
Submit copies of all debris clearance and survey reports to BEIS.


Timeline / EventRequirement / Action
Well Suspension or Abandonment – Consent Requirements
As early as possibleIf explosives are required, consult JNCC/DESNZ early to consider habitats and species issues under the Habitats Regulations.
As soon as need is knownSubmit summary of chemical use/discharge to DESNZ via a Well Intervention Application, even if already covered in a Drilling Operations or Decommissioning Operations Application.
As soon as need is knownIf any deliberate oil release is planned, obtain an Oil Discharge Permit. This must be included in the Well Intervention Application and will trigger permit issue.
As soon as need is knownIn exceptional cases, a FEPA licence may be required for seabed deposits (e.g. rock dumping over wellhead). Submit details in the Well Intervention Application.
Well Suspension or AbandonmentGeneral category for the above actions.
Key Compliance
Ensure compliance with all licence, exemption, or consent conditions.
Apply technology and techniques to prevent or reduce chemical discharges.
Monitor and record all chemical use and discharges. Report quantities to the UKOOA EEMS Coordinator.
Report chemical spills to DESNZ using PON1.
Report oil sheens or spills to HM Coastguard and DESNZ using PON1.

Onshore Activities

New Onshore PipelineNew Onshore ProjectModification to Onshore ProjectWaste Disposal

Timeline / EventRequirement / Action
Approval of New Onshore Pipeline Projects – Consent Requirements
14 months +Confirm requirement for Environmental Impact Assessment (EIA) under the relevant regulations (Pipeline Works, Public Gas Transporter Pipeline Works, Town and Country Planning, Environmental Impact Assessment (Scotland), or Infrastructure Planning Regulations).
14 months +Request a screening opinion to confirm if EIA is required. Request a scoping opinion to define scope of the EIA. Licensing authority must respond within statutory timelines.
14 months +Identify potential requirement for environmental permitting under Pollution Prevention Control (PPC) regulations.
As early as possibleIdentify whether project occurs near protected habitats or species under the EU Habitats Directive. If so, additional measures and a Habitats Regulatory Assessment may be required.
> 12 months (depending on project size and environmental sensitivities)Undertake informal consultation with the Local Planning Authority, statutory consultees, and relevant agencies.
> 12 monthsUndertake full Environmental Impact Assessment and prepare Environmental Statement (ES).
6 monthsIdentify whether authorisations are required under the Water Environment (Controlled Activities) (Scotland) Regulations (CAR).
4 monthsSubmit applications for required CAR authorisations.
4 months – 2 monthsSubmit application for Pipeline Construction Authorisation (PCA) and/or Planning Permission with ES (if required). This includes a 16-week regulatory consideration period.
4 months – 2 monthsComplete required advertising of ES in local press and on-site notices.
4 months – 2 monthsPublic consultation period on PCA Application (28 days).
Decision stagePlanning application decision issued.
Decision stagePCA decision issued.
Pipeline Construction CommencementWork may begin following approvals and compliance with all conditions.
Key Compliance
Ensure all commitments made in the ES are implemented in the detailed design and operation of the pipeline.
Ensure all planning conditions of consent are met, especially where they may update or override ES commitments.
Ensure all requirements of pollution control and IPPC regime applications are complied with.


Timeline / EventRequirement / Action
Approval of New Onshore Projects – Consent Requirements
16 months +Identify relevant Planning Authority. Usually this will be the Local Planning Authority (LPA), except where a project is classed as a National Significant Infrastructure Project (NSIP) in England and Wales, in which case the Infrastructure Planning Commission (IPC) applies.
15 months +Determine requirement for Environmental Impact Assessment (EIA) through Screening under regulations. A formal screening request can be submitted to the LPA for confirmation.
14 months +Determine scope of EIA by requesting a Scoping Opinion from the LPA. This involves consultation between developer, LPA, statutory consultees and stakeholders.
As early as possibleIdentify whether project occurs near protected habitats or species under the EU Habitats Directive. If so, a Habitats Regulatory Assessment may be required.
12 months + (depending on project size and environmental sensitivities)Undertake Environmental Impact Assessment and prepare an Environmental Statement (ES).
28 weeksIf deemed a “major development” under the Planning Act 2008, conduct pre-application consultation. Sufficient environmental information must be available, but a final ES is not required before consultation.
16 weeksSubmit ES along with the Planning Application and supporting documentation to the LPA for consideration.
16 weeksComplete required advertising of the ES, including publishing notices in local newspapers and displaying site notices.
Project ApprovalApplication decision issued by the relevant authority.
Key Compliance
Ensure all commitments made within the ES are delivered through detailed design and project implementation.
Ensure all planning conditions of consent are met, particularly where they update or override ES commitments.


Timeline / EventRequirement / Action
Approval of Onshore Project Modifications – Consent Requirements
16 months +Identify relevant Planning Authority. Normally this will be the Local Planning Authority (LPA), except where the project is a National Significant Infrastructure Project (NSIP), which falls under the Infrastructure Planning Commission (IPC).
16 months +Determine the need for Environmental Impact Assessment (EIA) of the proposed modifications, including consideration of case law (e.g. Baker case) concerning changes or extensions to approved developments.
15 months +Optionally submit a formal screening request to the LPA to confirm their interpretation of EIA requirements.
If no EIA requiredProceed to application for modifications to planning permission.
14 months +Submit request for a Scoping Opinion to the LPA. This should involve consultation between developer, LPA, statutory consultees, and other stakeholders. Consider whether a full EIA is required or whether an addendum to an existing ES is sufficient.
As early as possibleIdentify whether the development affects protected habitats or species under the EU Habitats Directive. A Habitats Regulatory Assessment may be required.
12 months + (depending on project size and environmental sensitivities)Undertake Environmental Impact Assessment and prepare Environmental Statement (ES).
28 weeksIf classed as a “major development” under the Planning Act 2008, conduct pre-application consultation. Sufficient environmental information should be available, but the final ES is not required before consultation begins.
16 weeksSubmit ES or ES Addendum along with application for modification to planning permission and other supporting documents to the LPA.
16 weeksComplete required advertising of the ES, including notices in local newspapers and at the project site.
Project ApprovalApplication decision issued. Options for appeal may apply.
Key Compliance
Ensure all commitments made within the ES are delivered through detailed design and project implementation.
Ensure all planning conditions of consent are complied with, particularly where they update or override ES commitments.


TimescaleRequirement / Action
Before Waste Transfer
- Ensure Transfer Notes for any Controlled Waste are in place and that the Waste Carrier is appropriately registered before transfer.

- Ensure Consignment Notes for Special/Hazardous Waste are completed.

- Ensure correct Transportation Records are completed for any Radioactive Waste.
Before Waste Disposal
- Minimise waste to landfill as far as possible and ensure the correct landfill site for waste type is selected.

- Ensure the waste disposal site has the correct Waste Management Licence in place.
Key Compliance
- Ensure waste is correctly segregated to meet recycling and reuse objectives.

- Ensure appropriate authorisations and placards are displayed.

- Encourage waste minimisation and recycling/reuse/recovery of waste as far as possible.

Working together, producing cleaner energies

Secure the Future of the North Sea

📬 Use our Email Your MP tool to make your voice heard. It only takes two minutes to back Britain’s energy future.

This will close in 0 seconds