North Sea energy operators must work together, says OEUK

23 November 2026

Collaboration and co-ordination are essential to secure vessels, skills and ports for successful oil and gas decommissioning alongside offshore wind development, says the 2026 Decommissioning Insight published by Offshore Energies UK today.

The report says earlier coordination will secure specialist vessels, engineering capability, skilled workers and port capacity.

Without this planning, competition for vessels, ports and skilled people will drive up costs and risk decommissioning targets being missed, it warns.

It forecasts £24.7 billion of UK Continental Shelf decommissioning expenditure between 2026 and 2035, covering 1,834 wells, 135 topsides and 126 underwater structures.

At the same time, offshore wind construction is expected to place growing demands on many of the same specialist resources.

The report identifies two periods of particular pressure over the next decade. New offshore wind capacity is forecast to peak at 5.20 GW in 2029, followed by sustained additions of more than 3 GW a year from 2031 to 2035. Both periods overlap with major decommissioning workloads.

The Central North Sea alone which covers the area East of Scotland, is forecast to account for 56% of decommissioning expenditure over the decade. OEUK says maintaining a dependable pipeline of work will be important as specialist resources move from Northern North Sea and West of Shetland programmes into long-term Central North Sea activity to the East of Scotland

The Decommissioning Insight identifies five priorities:

  • Provide earlier, more detailed information on confirmed work and timings
  • Combine compatible projects where possible
  • Secure specialist capacity earlier
  • Invest in ports, yards and recycling facilities to support dismantling and recycling of material
  • Maintain transparent information on project progress and its value to the UK economy

OEUK’s Supply Chain Principles already promote better commercial practices including appropriate risk allocation, prompt payment, effective tender engagement and improved visibility of future work.

The report warns, however, that a visible pipeline of work is not the same as secured delivery capacity. Converting the opportunity into UK jobs and investment requires earlier commitments that allow suppliers to invest confidently in equipment, facilities and people.

Mark Wilson, OEUK’s energy operations director, said:

“Coordinating decommissioning and offshore wind therefore presents an opportunity to keep the UK’s offshore industrial base working as the energy mix changes, safely dismantling legacy infrastructure and building the next generation of offshore energy.

“This is a major industrial opportunity for the UK, but it will not happen by accident. Oil and gas decommissioning and offshore wind increasingly need the same people, vessels, ports and engineering expertise.

“We need to plan across both sectors, align schedules and give suppliers sufficient confidence to invest. Earlier decisions and sustainable contracts will help prevent bottlenecks, control costs and keep valuable work and expertise in the UK.”

The report is available 2026 Decommissioning Insight and there is also a summary of report here .

OEUK is bringing operators, suppliers, regulators and academics together at its 2026 Offshore Decommissioning Conference from 23rd to 25th November in St Andrews, Scotland to identify practical solutions.

ENDS