Member news

Lynx Line opens for business: Kellas Midstream, NSMP

18 April 2024

Kellas Midstream and North Sea Midstream Partners (NSMP) announced the successful commissioning of the Lynx Line April 16.

Linking the Central Area Transmission System to the Teesside Gas Processing Plant, the line is a win-win for both companies, NSMP CEO Sayma Cox said. It delivers optionality for North Sea producers and ensures security of operation of a major UK gas transmission system.

Originated and funded by NSMP, the project was delivered on schedule and on budget within six months of a construction agreement being signed between the relevant parties.

The Lynx Line project would not have been possible without the collaboration and support NSMP received from Kellas, the Lynx Line anchor customers and project partners Camm-Pro, Wood and PX Group.

Kellas Midstream COO Alan Murray said that NSMP, the CATS terminal owners and his own company’s customers have demonstrated our collective expertise in safely delivering a fast-paced project. “We look forward to continuing our collaboration to meet the evolving needs of our customers,” he said.


Share this article

Working together, producing cleaner energies